Infrastructure

 

I
Area of land  allotted (in acres)
 
Whether land transferred in the Name of Samiti
 
Vidyalaya shifted to permanent buildings on 
:  31.19 acres
 
:  Yes
 
 
:  Yes
ii
Status of Boundary Wall
 
a.  Brick Wall
b.  Barbed wire fencing 
: Completed
 
 Stone wall & height increased by barbed wire
iii
Permanent buildings constructed
:  CPWD pattern
iv
School building 
: Complete
v
Dormitories
:  Boys 02 Nos.
   with Warden Residence 08 Nos.  
 
 
:  Girls 01 Nos.
   with Warden Residence 04 Nos.  
vi
Kitchen/dining Hall
 
No. of shifts required for all students  to take food 
:  Complete 
 
  One
vii
Principal Residence 
:  01 No.
viii
Staff Quarters 
: Type III = 20 Nos.
  Type II = 06 Nos.
  Type I  = 06 Nos.
  SP Sheds converted into Staff Qrs.: NA
ix
M.P. Hall 
: Not available
x
Workshop 
:  Not available
xi
Type of O.H. Tank
 
Its capacity
 
Present Status 
: Shaft type / Column based
 
:  1 lakh litres
 
: Working satisfactory
xii
U.G. tank
 
Its capacity
 
Present Status 
 
:  1 lakh litres
 
: Working satisfactory
xiii
D.G. Set 
:  Available
: ____________ make
: ______ KV
: Working
: Year of procurement 
xiv
Sewage Pump 
: ______ H.P.
xv
Water Pump 
: 04 H.P. Capacity
xvi
Electrification
 
Electric connection
Sub Station building
Street lighting
 
Numbers of hrs. during day when power supply is available on an average. 
 
 
: Urban Feeder
:  Complete
: 44 Nos. of Poles
 
:  Full day
  
xvii
Playfields
 
400 metre track
40 x 30 metre basket ball court
40 x 30 metre volley ball court
 
 
: Available
:  2 Nos.   – Available
:  4 Nos.   – Available  
xviii
Water supply
Tube Well
Hand pump
Connection from PHED 
 
: Potable, 04 Nos.- working
: Potable, 03 Nos.- working
: 03 hours supply in a day
xix
Rajiv Gandhi Smriti Van 
:  Not available
xx
Fire fighting arrangement 
:  Working
xxi
Last date of cleaning of
(a)   Septic tank
(b) Water tanks
 
: --
: 31-05-2008
xxii
Whether area around transformer is fenced
:  Yes
xxiii
Whether open wells, if any, are covered from top
:   NA
xxiv
Works taken up under M&R fund during current year and last year:-
 
 
Bath room doors repaired
Year
Name of work  (M&R)
Expenditure
(Rs. In lacs)
Cumulative expenditure during the year
2007-08
Bath room doors repaired
1.00 lac
1.00 Lac